Improving Laundry Storage with New Cabinets and Organizers
Killearn Estates Tallahassee, FL

Sam BurtonProject Manager

Stephanie JenDesigner
Final Project Cost: $36,314
Project Start Date: Nov. 13, 2024 Project Completion Date: Nov. 27, 2024
We finished 1 day ahead of schedule. Click here for detailed cost and timeline breakdown.
Project Summary:
New cabinets, counters and a few small layout changes improved the look and function of this laundry room. We also moved their icemaker under the countertop.
We moved the sink slightly and upgraded the storage with pull-out trash and hampers and added new thinscape countertops. We reused the existing appliances, kept the original floor tile and dog wash station.
Before/After
Drag the slider to see this project transformation!
New countertops and custom cabinets added laundry room storage while keeping the same layout.
McManus Kitchen and Bath is a full service remodeling company with an in-house design team and showroom right here in Tallahassee, FL.
Contact us to schedule a consult.
Key Updates:
Key Features
Materials and Fixtures
Our Favorite Things
Every project has a few things that really make it stand our or were special to the homeowner. Here are our favorites.

Dedicated space for laundry essentials

Deep single basin utility sink

Brushed Satin Nickel Drawer Pulls

Storage Above Washer and Dryer
Materials and Fixtures Used in This Project
Fixtures and Accessories
-
- Single Basin Utility Sink with Basin Rack from Ruvati
- Port Haven Single Hole Pull Down Bar Faucet from Pfister
- Davenport Pull in Brushed Satin Nickel from Top Knobs
- Rev-A-Shelf Pull Out Sliding Laundry Basket Hamper Drawer from Build Laundry Room Storage
- Rev-A-Shelf Under Sink Pull Out Cleaning Organizer from Build
Timeline, Challenges & Solutions
There were no significant challenges on this project. We did discover a minor amount of mold behind the cabinets but were able to mitigate it easily. And we had to re-run the icemaker line as the previous installer and run it through the cabinets. These issuses did not affect the project timeline.
Total project length was 2 weeks and 5 day
-
- Proposed start date: November 13, 2024
- Actual Start Date: November 13, 2024
-
- Proposed Completion Date: December 2rd 2, 2024
- Actual Completion Date: November 27th, 2024
The project ran just slightly ahead of schedule.
Project Costs
Initial Estimate: $33,210 | Fixed price proposal: $35,747
The final proposal was about $2500 more that our original estimate, a difference of about 7%. This was mostly due to labor costs being a little higher than expected.
Laundry Room Storage
Change Orders: $566.41
We needed to reroute the water lines for the ice maker and refrigerator as the previous contractor had installed them through the cabinets instead of in the wall.
FInal Project Cost: $36,314 (includes all change orders)
Cost Breakdown
Installation Labor35%
Materials and Fixtures25%
Design and Project Management Costs20%
Sales Tax and Shipping4%
Overhead and Profit10%
Change Orders3%
Project Photos and Video
Before Photos
Final Project Photos
Ready to Explore Ideas?
Our Design and Budget Consult Provides
-
- 3D drawings to help you visualize options
- A detailed estimate of materials and labor
- A chance to review material and fixture options in our showroom