Aging In Place Hall Bath Bannerman Community, Tallahassee Sam Burton, Project Manager Caitlin Tindell, Designer Final Project Cost: $59,177 Project Start Date: Oct. 15, 2024 Project Completion Date: Dec. 9, 20241 week over schedule due to the Thanksgiving holiday....
Maximizing Space in A Master Bath Bannerman Community, Tallahassee Sam Burton, Project Manager Caitlin Tindell, Designer Final Project Cost: $62,373 Project Start Date: Aug. 13, 2024 Project Completion Date: Oct. 18, 20242 week over schedule due to a...
Jack and Jill Bathroom in Lake Jackson Lake Jackson, Tallahassee Elliot Holtom, Project Manager Stephanie Jen, Designer Final Project Cost: $86,840 Project Start Date: Oct. 7, 2024 Project Completion Date: Nov. 26, 2024We finished on schedule. Click...