How to Create and Protect Your Remodeling Timeline
Plan first, then build
PLANNING
DESIGN AND SELECTIONS
PERMITS AND ORDERING
BUILD AND FINISH
PRO TIPMake all your design decisions in advance. Have all your materials delivered before you start. That will help avoid unexpected delays or surprise costs.
Bath Remodel Timeline
Here’s a realistic timeline for a high quality, custom gut renovation of a guest bathroom done by a licensed contractor using professional installers. This timeline is a little generous, it’s better to plan extra time vs unexpected delays.
DESIGN
3-6 weeks to create 3D drawings, floorplans & elevations, make material selections, review everything for accuracy and create a detailed project schedule.
PERMITS
Permits for a small bath remodel in Tallahassee generally only take a few weeks.
LEAD TIME FOR MATERIALS
Expect 4-8 week lead time for quality materials. If you are using big box store materials (which we do not recommend) it could be faster.
CONSTRUCTION:
-
- 1 day demo
-
- 1 day rough elec and rough plumbing
-
- 1 day framing & blocking
-
- 2 days drywall
-
- 1 day prime walls & ceiling
-
- 1 day waterproofing shower
-
- 5 days tile
- once tile is done you can template for shower glass – it can take 3 weeks for the shower glass to be fabricated and installed)
- 5 days tile
-
- 1 day vanity install and trim work
-
- 1 day template countertops
- It can take a week or more to fabricate and install the countertops
- 1 day glass install
- 1 day countertop install,
- 1 day plumbing trim out,
- 1 day elec trim out,
- 1 day final paint
- 1 day template countertops
PUNCHLIST
Depending on quality of work allow 1-2 weeks for punchlist items. Some contractors, like McManus Kitchen and Bath take care of punclist items throughout the project. other wait unitl the end, which can add days or week to the project.
Total Time To Complete
So a typical guest bath remodel can take 4-6 weeks depending on the exact scope of work and lead time for shower glass and countertops.
Have your contractor create a detailed schedule before they start… One that outlines what should happen every day.
How to Get Your Estimate
Our design and budget consult helps you customize your remodeling budget with 3D Designs + ‘Good-Better-Best’ estimate.
The consult process has 3 steps:
1. Discovery Call
2. Home Visit
3. Showroom Visit
Tired of vague ‘low bid, bait and switch’ estimates? Discover how our Design and Budget Consult helps you plan your remodel with clear, honest pricing.
The value of realistic planning
Explore ‘good-better-best’ options in our showroom
What’s Included:
The consult consists of a 60-min home visit, followed by a 90-min personalized design & budget review in our showroom.
It includes 3D layout drawings and a ‘good-better-best’ estimate. Consult Fees start at $225.