

Project Start Date: Jan 23, 2023 Project Completion Date: March 23, 2023
The project was finished 9 days behind schedule. Click here for a detailed cost and timeline breakdown.
This was our 3rd project for this family and the a last room in their home that needed updating. When they first came to us with the idea of fitting a shower and a double vanity in the girls bathroom I was skeptical if it could be done in such a small space. But after some creative design work we worked it out!
Timeline
Proposed project start date: Jan 23, 2023 Actual Project Start Date: Jan 23, 2023
Proposed Completion Date: March 23, 2023 - Actual Completion Date: March 17th 2023
We started design on October 18th, finalized everythings on Nov 29th 2022 and scheduled the project start for Feb 28th 2023. The project was completed on time on April 27th.
Budget vs Final Price
Our initial budgets are usually very accurate and this was no exception.
Change Orders
On this project there Just one change order due to a miscommunication in design. In design the client assured us that their current bath fan was vented through the roof, as is required by building code. Unfortunately at our pre-construction meeting we realized it was not. This resulted in a $1361 change order for the extra roofing and HVAC
Drag slider to see the transformation!
Quote from the client:
"We're finally not embarrased by that bathroom anymore, and the girls love it"
Get a realistic, no pressure assessment of the options and costs for your project by scheduling a design and budget consult.








The girls bathroom would be shared by two teenagers so the homeowner had some specific requirements. Even though the bath was small she really needed two sinks and a shower area that was private. The solution was to create a corner shower which, though on the small side, left enough room for a 55" double vanity and plenty of room for the toilet.
Since this was a returning client they were already very familar with how we work so we just made an appointment with them to scan the room and get measurements.

The floor tile was new but the rest of the bath needed work.
The biggest issues were having only one sink for two girls sharing the bathroom, the outdated look and a lack of storage.
We also suggested that the lighting and ventilation needed improvement and the possiblity of adding storage.
Initial Concept - moving the window to create a corner shower and larger vanity
We played around with a few options but ultimately there was only one concept that worked well for the girls bath. It meant removing the large center window in the bath and replacing it with a smaller one over the new toilet location so we could create a corner shower.
Slide between images to see the 3D rendering vs the final photo
Because this was a retun client the design process went quite well. This homeowner had strong options and knew what she wanted.
The Final rendered design for the Girls Bathroom


Final 3D Renders of the Girls Bathroom
Now that Design was complete we ordered all their materials, finalized the project calendar and set the exact start date for their project. As material arrive we stored them in our warehouse until the project start date.
Construction on this project went quite well with very few surprises. The project manager did a great job and we wound up finishing a week ahead of schedule.